    PSSR Checklist: How to Pass a Pre-Startup Safety Review (OSHA PSM 1910.119(i))

    A Pre-Startup Safety Review is the last gate before hazardous chemicals enter the system. Here is what auditors actually look for, the five sections every PSSR must cover, and the common findings that delay startup.

    Reviewed by The QHSE Standard editorial team

    Fact-checked against ISO 45001, OSHA, EU OSH Framework Directive, and CCPS guidance. Independent of vendor influence — see our review methodology.

    What a PSSR Actually Verifies

    A Pre-Startup Safety Review (PSSR) under OSHA PSM 1910.119(i) is the formal field-verification that a new or significantly modified process is ready for safe startup. It is not a paperwork exercise — it is a physical walkdown that confirms construction matches design intent.

    The Five Required PSSR Sections

    1. Construction & equipment — built per specifications, materials of construction correct, instrumentation calibrated
    2. Procedures — operating, maintenance, emergency, and safe-work procedures are in place and current
    3. PHA recommendations — for new processes, PHA is complete and recommendations resolved or scheduled
    4. MOC actions — for modified processes, every Management of Change action item is closed
    5. Training — affected operators, maintenance, and contractors are trained and competent

    P&ID Walkdown — What to Look For

    • Every line, valve, instrument, and relief device on the as-built P&ID exists in the field
    • Tag numbers match
    • Bypasses, blinds, and temporary connections are documented or removed
    • Vents and drains discharge to safe locations

    Common PSSR Findings That Delay Startup

    • Missing or expired calibration on safety-critical instruments
    • Open MOC action items disguised as "punch list"
    • Operating procedures not updated to reflect design changes
    • Emergency isolation valves obstructed or hard to reach
    • Inadequate training records for new equipment

    Run Your Own PSSR

    Download the Pre-Startup Safety Review Checklist template — a 3-page structured PSSR with field-verification items, sign-off matrix, and OSHA PSM 1910.119(i) cross-references. Free, OSHA-aligned, ready to adapt.

    Software That Manages PSSR Workflow

    If you run multiple turnarounds or capital projects per year, manual PSSR tracking breaks down. EHS platforms with MOC + PSSR modules (Tekmon, Intelex, Sphera, ProcessMAP) close the loop between PHA recommendations, MOC action items, and PSSR sign-off — see our QHSE software comparison for vetted picks.

    PSSROSHA PSMProcess SafetyOil and GasPre-Startup

    Software covered in this category

    Browse all platforms →
    Not sure which fits? Get matched in 60s

    Looking for the Right QHSE Software?

    Take our 60-second quiz and get personalized recommendations.

    Get Matched — Free
    Back to all articles